To complement Tony's new studio facilities the greenstaff were commissioned to build some all-weather driving bays.....
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjibxqbos3v-VaboiQCq_EV79gpVS70eNKn06DaNIa7bkkuKLY7GuZmVEG3rTBJKXA1liTQLPGIktbwR-IV0V4yXbo-ZTZmXKEjEdf2sq4_V4izTBXv5xPFbfrpOpTtUzkztrZKve6cCK0e/s1600/20140312_133855.jpg)
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgTmMWAmSLMifNDARYB45R44nXzXGBlbGxp_XIqG_zZL9IX7-SZKCNMgs4ZY-gRBiYzlSRlxxxJhI3aGbyIlhOfJu6rCBMF_kxAO1va0FS-7acYPBWW2Th2_JArADkGCHg50hFwJASfkkG-/s1600/20140313_080437.jpg)
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjBSVnblRD_IOpUp0YVtmM0S1U1IGEm2vevCpRjD0Qg5yoyOituskqnjRdUt8Oz_HT8jAxPSxXIQUM3YhuLB7H4TOPsYG6dMu5RZUC3-z_QDxg3UhcpXYze4df79SsHSS2q0BRXmgr6xxsM/s1600/20140313_133742.jpg)
After excavating the site the sleeper surrounds were constructed and the bays filled with hardcore.
.
This was then levelled and compacted to form a firm base for the top layer of sharp sand.
Quite possibly the most important part of the operation.
Great care was taken to ensure the sand was compacted and levelled to the exact requirements needed for the laying of the synthetic turf.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjQCd24ECgogZ9Vv1E_wmk2WtOJRAcd22miuVIt3vS6cXnF4B5LMPkYeLCmAzjxOZaxQ59LID7V3b1lbhG4SyoiIpYOpAE5bO0wKFwzl_XYbLVfrZ1nLXSmerHpeHXYSbX9NKIoypim9ymd/s1600/20140403_115558.jpg)
Synthetic turf laid, trimmed to exact size and nailed into place.
Bay dividers put in place, new studio signs and a gravel entrance and the job is complete.
No comments:
Post a Comment